Year | Company | Work | Value in INR |
---|---|---|---|
13-Oct-22 | Nayara Energy Limited | Revamp work of FGC at Nayara Energy | 1,62,50,000.00 |
23-Aug-22 | RELIANCE INDUSTRIES LIMITED,JMD | Overhauling of single shaft type compressor (Model: SH) at RIL Jamnagar site | 27,50,000.00 |
15-Jul-22 | RELIANCE INDUSTRIES LIMITED,JMD | SEZ DHDS-2 & PTU unit Fabrication Jobs during shutdown Sep'22 | 1,87,37,711.00 |
27-Jun-22 | SIEMENS LTD | Overhauling job of integrally geared type compressor (Model: STC GC 40-3) at SAIL Bhilai | 2,596,000.00 |
24-May-22 | ONGC Petro addition Limited | Overhauling Services for PES Train-1/2 Extruder Mixer Gear Reducer | 6,300,000.00 |
15-Apr-22 | RELIANCE INDUSTRIES LIMITED,JMD | Contract for rotary jobs of PP plant S/D, RIL-HMD | 58,07,226.00 |
6-Apr-22 | RELIANCE INDUSTRIES LIMITED,HMD | Contract for Rotary jobs MEG2 S/D, RIL-HMD | 9,77,407.00 |
23-Mar-22 | SIEMENS LTD | Major overhauling of Steam Turbine,Overhauling job of Siemens Turbo Compressor & Gas Expander at MCPI Haldia | 5,841,000.00 |
22-Mar-22 | ONGC Petro addition Limited | Hiring of Mechanical Maintenance Services for overhauling of both PP Reactor Agitators & its accessories during Major Turn Around Shutdown | 1,32,30,000.00 |
11-Dec-2021 | HPCL-MITTAL ENERGY LIMITED | STRUCTURAL WORK OF VGO -3RD REACTOR AT HMEL REFINERY SITE,BATHINDA | 49,577,500.00 |
25-Mar-2021 | RELIANCE INDUSTRIES LIMITED | Fabrication, static, Rotary and associated scaffolding jobs at Jamnagar SEZ Complex | 42500000.00 |
25-Mar-2021 | RELIANCE INDUSTRIES LIMITED | Fabrication, static, rotary and associated scaffolding jobs at DTA Gasification Complex | 13921606.41 |
25-Mar-2021 | RELIANCE INDUSTRIES LIMITED | Fabrication, static, rotary and associated scaffolding jobs at SEZ Gasification complex | 20,882,409.61 |
25-Mar-2021 | RELIANCE INDUSTRIES LIMITED | Fabrication, static, rotary and associated scaffolding jobs at C2 Full GST Plants | 15,237,200.00 |
24-Jan-2020 | RELIANCE INDUSTRIES LIMITED | Rotary maintenance work | 58,625,832.00 |
6-Dec-19 | Thyssenkrupp Industries India Pvt. Ltd. | Work order (WO) for comprising of Receipt, Unloading, Stacking, Handling, Storage, Security of material at Site, onward transportation from storage yard to Erection point (Apx-2 to 3 KM depending on size and Height of consignment), Ground assemblies and Erection, Assistance for Commissioning, PG Test and Handing over of 3 X 120 TPH CFBC Boilers and its auxiliary for M/s. Haldia Petrochemicals Ltd. | 159,500,000.00 |
30-Sep-16 | Reliance Industries Ltd. Vill- Nagothane, Raigad, Maharashtra. EIC- Mr. Amar Dev) | OCASSIONAL FABRICATION & MAINTENANCE JOB | 10734000 |
30-Apr-16 | Reliance Industries Ltd. Vill- Nagothane, Raigad, Maharashtra. EIC- Mr. Amar Dev) | OCCASIONAL SCAFFOLDING JOBS | 4800000 |
30-Aug-13 | Reliance Industries Limited | Piping related jobs carried out during shutdown | 19,37,596.52 |
8-Aug-13 | Reliance Industries Limited | Piping related jobs carried out during shutdown | 18,85,351.36 |
12-Jun-13 | Reliance Industries Limited | Levelling, Alignment & Pre-commissioning of PAC Equipments, Agitators and other rotary Equipment. | 12,31,690.32 |
12-Jun-13 | Reliance Industries Limited. | Levelling, Alignment & Pre-commissioning of PAC Equipments, Agitators and other rotary Equipment | 2,19,21,732.63 |
23-May-13 | Reliance Industries Limited | Replacement of valves during shutdown | 91,62,958.00 |
14-May-13 | Reliance Industries Limited | Rotary Equipment Maintenance job during shutdown | 20,55,753.73 |
8-May-13 | Reliance Industries Limited | OCCASIONAL SCAFFOLDING JOBS | 32,00,000.00 |
7-May-13 | Reliance Industries Limited | Rotary Equipment Maintenance job during shutdown | 41,05,634.40 |
25-Apr-13 | Reliance Industries Limited | Erection and commissioning of G301X and other Rotary Equipment | 37,64,060.00 |
25-Mar-13 | Reliance Industries Limited | MAINT. JOBS IN LLDPE & BUT-1 PLANTS AT RIL NAGOTHANE | 90,00,000.00 |
25-Mar-13 | Reliance Industries Limited | MAINT. JOBS IN LDPE PLANTS AT RIL NAGOTHANE | 40,00,000.00 |
1-Feb-13 | Reliance Industries Limited | Occasional Boiler Maintenance Jobs | 40,00,000.00 |
27-Aug-12 | Reliance Industries Limited | Coke Drum block#3 switch valve piping modification | 5,05,620.00 |
11-Aug-12 | Reliance Industries Limited | Occassional Rotary Equipment Maintenance Jobs | 1,00,00,000.00 |
10-Aug-12 | Reliance Industries Limited | Occasional Static Equipment Maitenance & Fabrication jobs and & Occasional Coke Drum Related Jobs. | 3,60,00,000.00 |
1-Aug-12 | Reliance Industries Limited | Occasional Jobs Related to Coke Drum and Coke Handling System | 2,15,00,000.00 |
1-Aug-12 | Reliance Industries Limited | Occassional Rotary Equipment Maintenance Jobs | 3,11,00,000.00 |
1-Aug-12 | Reliance Industries Limited | Occassional Rotary Equipment Maintenance Jobs | 3,00,000.00 |
28-Jul-12 | Reliance Industries Limited | Occasional Bundle Puller Jobs | 55,00,000.00 |
24-Jul-12 | Reliance Industries Limited | Overhauling of rotary equipments during May'2012 shutdown at VCPVC plant | 250,787.52 |
7-Jul-12 | Reliance Industries Limited | Scaffolding job during Aromatics shutdown at Aromatics Plant | 22,51,605.74 |
3-Jul-12 | Reliance Industries Limited | Maintenance & Inspection of coils of steam generator 523-Y04 | 14,04,500.00 |
30-Jun-12 | Reliance Industries Limited | Rotary Equipment maintenance job at CPP, PP, Coker, Hydrogen, Sulphur, RTF, RRTF Plant | 5,35,91,565.00 |
30-Jun-12 | Reliance Industries Limited | Occasional Jobs Related to Coke Drum and Coke Handling System at Coker Plant | 2,02,84,534.00 |
30-Jun-12 | Reliance Ports & Terminal Limited | Preventive Maintenance & Overhauling of all type of Rotary Euip at RRTF Plan | 5,00,000.00 |
28-Jun-12 | Reliance Industries Limited | Overhauling of Agitators | 3,55,282.33 |
14-Jun-12 | Reliance Industries Limitedt | Compressor Overhauling in PVC/VCM plant | 23,59,560.00 |
30-May-12 | Reliance Industries Limited | Compressor overhauling at LLDPE plant | 2,47,641.44 |
26-May-12 | Reliance Industries Limited | Overhauling of rotary equipments during ACN shutdown | 176,180.48 |
8-May-12 | Reliance Industries Limited | Combution inspection of Gas Turbine #4 at CPP Plant | 4,31,462.40 |
8-May-12 | Reliance Industries Limited | Additional compensation for Feb'12 shutdown | 23,31,958.00 |
4-May-12 | Reliance Industries Limited | Rotary Equipment maintenance job in shutdown in PE Plant | 11,23,600.00 |
16-Apr-12 | Reliance Industries Limited | OCCASIONAL MAINTENANCE OF ROTARY EQUIPMENTS | 70,14,681.00 |
26-Mar-12 | Reliance Industries Limited | IBR piping job under CP-13 | 4,19,140.00 |
16-Mar-12 | Reliance Industries Limited | Compressor Motor removal & reinstallation in MEG Plant | 3,30,900.00 |
15-Mar-12 | Reliance Industries Limited | Occasional IBR Co-ordination Jobs | 10,00,000.00 |
6-Mar-12 | Reliance Industries Limited | Rotor removal & refixing of Generator_GT#3 | 2,64,720.00 |
6-Mar-12 | Reliance Industries Limited | Compressor Overhauling in MEG Plant | 20,95,700.01 |
9-Feb-12 | Reliance Industries Limited | Compressor Overhauling in PP Plant | 7,44,525.00 |
20-Jan-12 | Reliance Industries Limited | OVERHAULING OF EXTRUDER CMP250X-12AW | 15,44,200.00 |
17-Jan-12 | Reliance Industries Limited | Nozzle modification job in 241/242-S01 | 3,63,990.00 |
6-Jan-12 | Reliance Industries Limited | Extruder overhauling at PP Plant | 13,23,600.00 |
25-Nov-11 | Reliance Industries Limited | Compressor Overhauling in MEG Plant | 26,79,573.05 |
12-Nov-11 | Reliance Industries Limited | Rotary equipment o/h job. | 4,05,021.60 |
20-Oct-11 | Reliance Industries Limited | Combution inspection of Gas Turbine at CPP Plant | 3,83,844.00 |
12-Oct-11 | Reliance Industries Limited | Static job to facilitate IBR inspection in Sulphur units 452 & 453 at Sulphur plant | 6,72,830.00 |
30-Sep-2011 | EPIL | Assembly, erection/installation, testing & mechanical completion of coke cutting system and coke crushing system with conveyer for DCU unit at EOL refinery site, Vadinar | 8,934,300.00 |
26-Sep-11 | EPIL | Erection & Alignment of Steam Turbine | 23,052,700.00 |
22-Sep-11 | Reliance Industries Limited | Compressor Overhauling at Hydrogen Plant | 3,30,900.00 |
21-Sep-11 | Reliance Infrastructure Ltd. | Combustion & Boroscopic Inspection | 2,97,000.00 |
9-Sep-11 | Reliance Industries Limited | Expander Overhauling in PTA Plant | 15,22,140.00 |
3-Sep-11 | Reliance Industries Limited | Fin Fan Inspection & PM Job in PTA Plant | 6,83,860.00 |
3-Sep-2011 | EPIL | Replacement of impellers & modification in motor base plate of CDU/VDU/SGU/FCCU/UGS Unit during shutdown period at EOL refinery site. | 1,009,245.00 |
27-Aug-11 | Reliance Industries Limited | Rotary & Static Equipment Maintenance job of Offshore & Onshore plant at Kakinara Site | 7,34,61,868.00 |
24-Aug-11 | EPIL | Rotary Manpower deployment - Train- 1 for commissioning and Pre-commissioning activities | 6,442,755.36 |
1-Aug-11 | Reliance Industries Limited | MAAG pump (PRU 3-41) overhauling at HDPE-1 plant. | 4,36,788.00 |
27-Jul-11 | Reliance Industries Limited | Rotary equipment o/h job. | 5,65,839.00 |
8-Jul-11 | Reliance Industries Limited | Expander Overhauling in PTA Plant | 16,54,500.00 |
2-Jul-11 | Reliance Industries Limited | Rotary equipment o/h job. | 1,98,540.00 |
8-Jun-11 | Reliance Industries Limited | overhauling of compressor GIOP-K 201 of N2O2/IOP plant | 4,86,423.00 |
10-May-11 | Reliance Industries Limited | Maintenance of rotory Equipment | 1,92,97,982.00 |
13-Apr-11 | Reliance Industries Limited | Attending surprise job during Feb'11 shutdown at FCCU Plant | 5,39,600.83 |
21-Feb-11 | Reliance Industries Limited | Occassional Boiler Maintenance Job at CPP Plant | 72,00,000.00 |
9-Feb-11 | Reliance Industries Limited | M & I of plate type exchanger at PP Plant | 7,72,100.00 |
9-Feb-11 | Reliance Industries Limited | Compressor Overhauling in MEG Plant | 29,84,497.40 |
7-Feb-11 | Reliance Industries Limited | Attending surprise job during Feb'11 shutdown at FCCU Plant | 17,45,773.00 |
21-Oct-10 | Haldia Petro Chemicals | Rotary equipment maintenance job | 7,922,806.00 |
21-Sep-10 | Reliance Industries Limited | Rotary equipment o/h job. | 91,60,873.85 |
15-Jul-10 | Reliance Industries Limited | Rotary Equipment maintenance job at CPP, PP, Coker, Hydrogen, Sulphur, RTF, RRTF Plant | 3,47,50,000.00 |
Year | Company | Work | Value in INR |
---|---|---|---|
29-Jul-22 | RELIANCE INDUSTRIES LIMITED | Rotary Manpower Services for Extruder-5101 Gear box Overhauling Job | 40,00,000.00 |
5-Jul-22 | RELIANCE INDUSTRIES LIMITED | Rotary Equipments Overhauling Jobs during PP Line C Unit Shutdown at DTA Refinery -Jamnagar | 43,00,000.00 |
16-Dec-21 | RELIANCE INDUSTRIES LIMITED | Critical Rotary Equipments overhauling jobs in SEZ PP Unit Line 1 & 2 Shutdown at RIL-Jamnagar | 80,00,000.00 |
31-May-21 | THERMAX LIMITED | MISCELLANEOUS MECHANICAL WORK AT RIL UF+RO DTA JAMNAGAR. | 1,17,46,600.00 |
25-Jun-20 | RELIANCE INDUSTRIES LIMITED | Fabrication, static, Rotary and associated scaffolding jobs at Jamnagar SEZ Complex | 10,04,60,574.08 |
24-Oct-19 | HPCL-MITTAL ENERGY LIMITED | Arc Providing Static Maintenance Services at HMEL Refinery Site, Bathinda | 6,50,00,000.00 |
13-Jun-19 | Linde India Limited | Mechanical and Civil Erection work at BORL BINA PROJECT SITE VPSA PLANT | 2,36,00,000.00 |
31-Dec-16 | Reliance Industries Ltd. Vill- Meghpar, Padana, Jamnagar. EIC- K C Upreti (8454843486) | Erection of compressor at PCG | 5284639 |
31-Dec-16 | Reliance Industries Ltd. Vill- Meghpar, Padana, Jamnagar. EIC- K C Upreti (8454843486) | Levelling, Alignment & pre commissioning of Rotary equipment-PCG Unit, DTA | 14140012 |
31-Dec-16 | Reliance Industries Ltd. Vill- Meghpar, Padana, Jamnagar. EIC- K C Upreti (8454843486) | Preservation of rod mill | 6000000 |
31-Dec-16 | Thermax Engg. Const. Co. Ltd. Energy House, D-II Block, Plot No 38 & 39, MIDC area, Chichwad, Pune 411019 (EIC: Mr. N. Menon) | Labour charges towards Unloading, Physical Verification, Preparation of Materials Receipt Report, Storing/stacking, Inplant Transportation of all erection materials, fabrication of syn gas piping, and Dismantling & Erection of items as per work description, application of refractory & insulation, finish painting, & providing assistance during Commissioning of 6 Aux boilers at M/s. Reliance Utilities & Power Pvt Ltd., Jamnagar, Gujarat. | 32921480 |
31-Dec-16 | Thermax Engg. Const. Co. Ltd. Energy House, D-II Block, Plot No 38 & 39, MIDC area, Chichwad, Pune 411019 (EIC: Mr. N. Menon) | Labour charges towards Unloading, Physical Verification, Preparation of Materials Receipt Report, Storing/stacking, Inplant Transportation of all erection materials, fabrication of syn gas piping, and Dismantling & Erection of items as per work description, application of refractory & insulation, finish painting, & providing assistance during Commissioning of 9 HRSG boilers at M/s. Reliance Utilities & Power Pvt Ltd., DTA Area, Jamnagar, Gujarat. | 53595720 |
31-Dec-16 | Thermax Engg. Const. Co. Ltd. Energy House, D-II Block, Plot No 38 & 39, MIDC area, Chichwad, Pune 411019 (EIC: Mr. N. Menon) | Labour charges towards Pre shutdown, shutdown & post shutdown work at our 2 X 23.90 TPH site, at M/S. Reliance Industries Limited., Jamnagar, Gujarat | 43029163 |
31-Dec-16 | Thermax Engg. Const. Co. Ltd. Energy House, D-II Block, Plot No 38 & 39, MIDC area, Chichwad, Pune 411019 (EIC: Mr. N. Menon) | Labour charges towards assembly of 5 No. Evaporator modules each for FGC north & south Train at our 2 X 23.90 TPH FGCs at M/S. Reliance Industries Ltd., Jamnagar, Gujarat | 31070836 |
30-Sep-16 | Reliance Industries Ltd. Vill- Meghpar, Padana, Jamnagar. EIC- Unna Murikeyya (9998215214) | OCASSIONAL FABRICATION, STATIC MAINTENANCE & COKER SPECIIFC JOBS IN SEZ | 43600000 |
30-Sep-16 | Reliance Industries Ltd. Vill- Meghpar, Padana, Jamnagar. EIC- R. Mohana Rajan | BOILER MAINTENANCE JOBS IN DTA REFINERY ON CALL BASIS | 4000000 |
30-Sep-16 | Reliance Industries Ltd. Vill- Meghpar, Padana, Jamnagar. EIC- Anil Pahuja | OCASSIONAL FABRICATION, STATIC MAINTENANCE & COKER SPECIIFC JOBS IN DTA REFINERY | 29500000 |
31-Aug-16 | Reliance Industries Ltd. Vill- Meghpar, Padana, Jamnagar. EIC- K C Upreti (8454843486) | Equipment preservation job in DTA Area | 11113353 |
31-Aug-16 | Reliance Industries Ltd. Vill- Meghpar, Padana, Jamnagar. EIC- K C Upreti (8454843486) | Equipment preservation job in SEZ Area | 1559050 |
31-Aug-16 | Thermax Engg. Const. Co. Ltd. Energy House, D-II Block, Plot No 38 & 39, MIDC area, Chichwad, Pune 411019 (EIC: Mr. N. Menon) | Labour charges towards Unloading, Physical Verification, Preparation of Materials Receipt Report, Storing/stacking, Inplant Transportation of all erection materials and erection & providing assistance during Commissioning 1 No. 275 TPH, 112.8 kg/cm2, 512 +/- 5 deg. C. HRSG Boiler at M/s. Reliance Utilities & Power Pvt Ltd., Jamnagar, Gujarat. | 51325640 |
31-Aug-16 | Thermax Engg. Const. Co. Ltd. Energy House, D-II Block, Plot No 38 & 39, MIDC area, Chichwad, Pune 411019 (EIC: Mr. N. Menon) | Labour charges towards unloading, physical verification, storing/stacking, inplant transportation of all project materials and erection & providing assistance during commissioning of 1 no. 9.44 MMK/Cal/Hr Hot oil heater at RIL, Jamnagar, Gujarat. | 8052917 |
31-Jul-16 | Reliance Industries Ltd. Vill- Meghpar, Padana, Jamnagar. EIC- K C Upreti (8454843486) | Levelling & Alignment of Rotary equipment-ROGC & MEG Unit, C2 complex, DTA | 11969463 |
31-Jul-16 | Reliance Industries Ltd. Vill- Meghpar, Padana, Jamnagar. (Refinary Complex) | Occasional rotary equipments maintenance jobs on call basis | 15400000 |
31-Jul-16 | Reliance Industries Ltd. Vill- Meghpar, Padana, Jamnagar. EIC- HOD of each unit. | Occassional Rotary Equipment Maintenance Jobs | 39400000 |
30-Jun-16 | Reliance Industries Ltd. Vill- Meghpar, Padana, Jamnagar. EIC- K C Upreti (8454843486) | Equipment preservation job in DTA Area | 11821420 |
30-Jun-16 | Reliance Industries Ltd. Vill- Meghpar, Padana, Jamnagar. EIC- K C Upreti (8454843486) | Equipment preservation job in SEZ Area | 8221663 |
30-May-16 | Reliance Industries Ltd. Vill- Meghpar, Padana, Jamnagar. EIC- K C Upreti (8454843486) | Installation, Levelling, Alignment & pre commissioning activities of Rotary equipment-PX4 Projects | 21848424 |
1-May-13 | HPCL-Mittal Energy Limited | Rotary Equipment Maintenance job | 1,68,54,000.00 |
15-Apr-13 | Indian Oil Corporation Limited | Providing manpower and technical services for Major overhauling and testing of GT-3 generator at Mathura | 11,68,544.00 |
8-Apr-13 | HPCL-Mittal Energy Limited | Static Equipment Maintenance job | 2,00,00,000.00 |
4-Feb-13 | Essar Oil Limited | Occasional Coke Drum Specific PM jobs & Static Equipment Maintenance job | 67,12,924.00 |
21-Jan-13 | Indian Oil Corporation Limited | Lining up of agency for carrying out ARC jobs (Hot & Cold) for Process units of PNC". | 2,51,07,520.10 |
28-Jul-12 | Reliance Petroleum Limited | Occasional Bundle Puller Jobs | 35,00,000.00 |
30-Jun-12 | Reliance Petroleum Limited | Occasional Coke Drum Specific PM jobs & Static Equipment Maintenance job at Coker Plant | 3,89,31,184.00 |
20-May-12 | HPCL-Mittal Energy Limited | Pre-commissioning and commissioning including chemical cleaning and passivation work for Guru Gobind Singh Refinery Project- Bathinda | 23,20,00,000.00 |
26-Mar-12 | Reliance Petroleum Limited | Delta valve replacement done at Coker Plant | 30,12,400.00 |
14-Mar-12 | Essar Oil Limited | Occassional Rotary Equipment Maintenance Jobs | 3,90,00,000.00 |
2-Mar-12 | Essar Oil Limited | Occasional Coke Drum Specific PM jobs & Static Equipment Maintenance job | 92,00,000.00 |
20-Feb-12 | HPCL-Mittal Energy Limited | Bearing replacement of ID/FD Fan | 3,62,536.00 |
23-Jan-12 | Reliance Petroleum Limited | IBR piping job_HMU | 16,30,000.00 |
21-Jan-12 | HPCL-Mittal Energy Limited | Manpower services for insulation work | 20,00,000.00 |
12-Jan-12 | HPCL-Mittal Energy Limited | Pre-commissioning & Commissioning | 26,06,75,200.00 |
4-Jan-12 | Essar Oil Limited | Rotary Manpower deployment - Train- 1 for commissioning and Pre-commissioning activities | 35,07,540.00 |
23-Dec-11 | Essar Oil Limited | SIPL SEP 2011 S/D WORK | 25,77,523.46 |
22-Dec-11 | HPCL-Mittal Energy Limited | Manpower services for Pre-commissioning & Commissioning & start upactivity | 20,00,000.00 |
22-Dec-11 | HPCL-Mittal Energy Limited | Manpower services for insulation work | 20,00,000.00 |
19-Dec-11 | Essar Oil Limited | Sep'11 SD CCR RGC 30K001 | 17,64,800.00 |
29-Oct-11 | Bharat Oman Refineries Limited | Static Equipment Maintenance Job | 3,46,78,320.00 |
10-Oct-11 | HPCL-Mittal Energy Limited | Execution of LPG unloading facility in offsite | 17,64,806.00 |
4-Oct-11 | Reliance Petroleum Limited | Additional Compensation job done under maintenance ARC at Coker Plant | 61,407.00 |
1-Sep-11 | Indian Oil Corporation Limited | Emergency /Planned Maintenance Jobs of GT I,II,III,IV & V at Gujarat Refinery | 3,99,000.00 |
27-Aug-11 | Reliance Petroleum Limited | Hydrotest of the Process Hoses at CES | 2,85,860.00 |
25-Aug-11 | HPCL-Mittal Energy Limited | Rotary Equipment Maintenance job | 2,00,00,000.00 |
19-Aug-11 | HPCL-Mittal Energy Limited | Cleaning of column at MS Block unit | 60,66,500.00 |
30-Jul-11 | Reliance Petroleum Limited | Compressor Overhauling at Aromatics Plant | 3,25,000.00 |
24-Jun-11 | Indian Oil Corporation Limited | Inspection & Replacement of Bearing of Gas Turbine generator, GTG - 1 at MR. | 3,60,000.00 |
14-Jun-11 | Essar Oil Limited | Rotary Manpower deployment - Train- 1 for commissioning and Pre-commissioning activities | 64,42,755.36 |
27-May-11 | Bharat Oman Refineries Limited | Static Equipment Maintenance Job | 49,44,891.00 |
13-May-11 | HPCL-Mittal Energy Limited | Cleaning of column at VGO and DHDT unit | 1,15,08,702.00 |
6-May-11 | Essar Oil Limited | Deployment of manpower & resources for fabrication & Static Jobs in VPCL for expansion activity | 8,13,765.83 |
3-May-11 | HPCL-Mittal Energy Limited | Hydrotesting of pipe loops | 3,75,02,000.00 |
30-Apr-11 | Bharat Oman Refineries Limited | Static Equipment Maintenance Job | 4,09,95,026.00 |
15-Apr-11 | Essar Oil Limited | Compressor overhauling during major shutdow in 2011 | 23,16,300.00 |
12-Mar-11 | Reliance Petroleum Limited | IBR liasioning for exchangers, welding of skin thermocouple in heater # 4 and compensation for september at Coker Plant | 3,52,695.00 |
2-Feb-11 | Reliance Petroleum Limited | Occasional Coke Drum Specific PM jobs at Coker Plant | 12,82,300.00 |
2-Nov-10 | Indian Oil Corporation Limited | Generator Overhauling testing & cryogeniccleaning of steam | 27,36,000.00 |
25-Oct-10 | HPCL-Mittal Energy Limited | Pre Commissioning & Commissioning | 2,14,33,516.00 |
4-Jan-10 | Indian Oil Corporation Limited | Support Service for Rotary equipment, Electrical equipment, instrumentation equipment maintenance in BXP Units at Barauni Refinery | 1,51,20,000.00 |
7-Oct-09 | Bharat Oman Refineries Limited | Rotary Equipment maintenance job. | 1,67,15,725.00 |
Year | Company | Work | Value in INR |
---|---|---|---|
20-Sep-21 | Gujarat State Electricity Corporation Limited | Overhauling of the H.P Turbine cylinder in LMW / LMZ design BHEL makes 200 MW Unit No 3 at GSECL Ukai TPS. | 39,15,000.00 |
14-Sep-21 | Gujarat State Electricity Corporation Limited | 4X125MW Surat Lignite Power Plant; Biennial Maintenance contract of Unit 1 to 4 Turbine & its auxiliaries and balance of plant equipment for the period of two years (2021-23) | 2,06,12,654.75 |
25-Mar-21 | JAMNAGAR UTILITIES & POWER PVT LIMITED | Fabrication, static, rotary and associated scaffolding jobs at JMD SEZ | 1,50,00,000.00 |
25-Mar-21 | JAMNAGAR UTILITIES & POWER PVT LIMITED | Fabrication, static, rotary and associated scaffolding jobs at C2 CPP Complex | 72,43,800.00 |
3-Nov-20 | BGGTS Private Limited | Fuel conversion project- Offbase and Onbase -2 Units along with required no. of manpower and tools | 97,56,402.00 |
20-Jun-20 | NTPC Limited | Biennial Maintenance Contract for Gas Turbine & Auxiliaries at Dadri Gas Power Station (2020-22) | 1,24,71,621.91 |
27-Nov-19 | NEEPCO Limited | Assistance in work for carrying out operation and maintenance of 65.42 mw gas turbine and 35.58 MW steam turbine along with various related field activities of TGBPP at MONARCHAK | 2,23,21,912.00 |
13-Sep-19 | BHEL | Erection, Testing, commissioning Trial run, PGTR and handing over of 1X59.3 MW GTG, 1X 15.5 MW STG, Deaerator system, 11KV Emergency DG Sets, HP and LP Pumps, Fire Fighting system, Associated static and rotating auxiliaries of GTG and STG etc. at 1X75 MW VISAKH REFINERY MODERNIZATION PROJECT (VRMP), Visakhapatnam, Andhra Pradesh | 5,94,00,000.00 |
9-Aug-19 | K C Cottrell India Private Limited | Mechanical Erection activities for renovation and modernisation for ESP Unit 1,2,3 of 210 MW WBPDCL , Kolaghta | 14,53,92,562.00 |
1-Apr-19 | NTPC Limited | Biennial Contract for Mechanical Maintenance at NTPC Anta | 2,01,60,792.89 |
9-Aug-18 | K C Cottrell India Private Limited | Electrical Erection activities for renovation and modernisation for ESP Unit 1,2,3 of 210 MW WBPDCL , Kolaghta | 1,47,31,436.00 |
9-Aug-17 | K C Cottrell India Private Limited | Civil Erection activities for renovation and modernisation for ESP Unit 1,2,3 of 210 MW WBPDCL , Kolaghta | 9,04,72,650.00 |
25-Apr-12 | Reliance Utilities Private Limited | Bearing inspection for the purpose of grooving on bearing housing cover | 2,00,000.00 |
17-Feb-11 | Reliance Utilities Private Limited | Occassional Boiler Maintenance Job at CPP Plant | 72,00,000.00 |
30-Jun-07 | Govt. of Arunachal Pradesh | Renovation and modication of Hydro power plant | 1,68,12,900.00 |
30-Jun-07 | Govt. of Arunachal Pradesh | Erection & commissioning of hydro power plant | 1,43,10,000.00 |
Year | Company | Work | Value in INR |
---|---|---|---|
29-Aug-21 | Matix Fertilizers and Chemicals Limited | PMS (Plant Maintenance Services) Mechanical & Electrical | 2,19,07,13,070.00 |
27-Jun-19 | Matix Fertilizers and Chemicals Limited | Services Required for IPM | 4,02,37,870.00 |
Year | Company | Work | Value in INR |
---|---|---|---|
13-Jan-20 | Thermax Babcock & Wilcox Energy Solutions Pvt. Ltd | Labour charges for Unloading, Physical Verification, Preparation of MRR, Storage, in plant Transportation of all erection materials and Erection & providing assistance during Commissioning including trial run, PAC & FAC of 1 X 175 MW TG sets along with accessories, as per BOQ sent, for our BFG based Power Plant M/s JSW Steels Ltd; Dolvi. | 2,30,10,000.00 |
01-Oct-14 | Bhilai Engineering Corporation Limited | Erection & providing ssistance in Commissioning of 4 x 25 TPH West Heat Recovery Boiler at COB #11 at Bhilai Steel Plant, Bhilai, CH. | 3,11,00,000.00 |
01-Dec-13 | Bhilai Engineering Corporation Limited | Erection & providing assistance in Commissioning of 4 x 25 TPH West Heat Recovery Boiler for "ISP CDCP # 11 project, at IISCO Steel Plant, Burnpur, West Bengal | 3,12,00,000.00 |
30-Jun-12 | Thermax Engineering Construction Company Ltd. | Erection, assistance during commissioning of 1 x42.3 TPH , WHRB Boiler at M/s.Super Smelter Ltd., Jamuria , West Bengal, | 73,00,000.00 |
30-Jun-12 | Thermax Engineering Construction Company Ltd. | Erection and providing assistance during commissioning of 1 x 24 TPH , 67 Kg/cm2, 490 +/- 5 Deg. C, AFBC Boiler at Seven Star Steels Ltd, Jharsuguda, Orissa. | 55,00,000.00 |
30-Sep-11 | Thermax Engineering Construction Company Ltd. | Erection, assistance during commissioning of 1 x115TPH, 91 kg/cm2, 525 Deg. C AFBC Boiler at M/s. Ankit Metal & Power Ltd, Bankura. | 1,66,95,886.00 |
30-Jun-11 | Thermax Engineering Construction Company Ltd. | Erection, testing and commissioning of mechanical package-1 for 1 x 20 MW CPP at KJS, Barbil, Orissa | 1,51,27,500.00 |
31-Jul-10 | TECHNO ELECTRIC AND ENGG. CO. LTD. \ | Erection, fabrication , assembly of WHRB (CBBT-631) of capacity 49.3 TPH & 69 kg/cm2 at M/s. Techno Electric & Engineering Co Ltd site, Makarampur, Kharagpur, West Bengal | 1,25,00,000.00 |
30-Jun-10 | Thermax Engineering Construction Company Ltd. | Erection, assistance during commissioning of 1 x 35 TPH x 70 Kg/cm2,x490 Deg. C., AFBC Boiler & 1 x 41.5 TPH x 69 Kg/cm2 x 490Deg. C. WHRB Boiler at M/s. Super Smelter Ltd., Jamuria, West Bengal, | 1,10,00,000.00 |
07-Oct-09 | Thermax Engineering Construction Company Ltd. | Erection, assistance during commissioning of 1 x 35 TPH, 66 Kg/cm2, 495 Deg. C., Bi-Drum AFBC Boiler at Drolia Electrosteel Ltd, Raipur Odisa | 61,29,768.08 |
30-Jun-07 | Thermax Engineering Construction Company Ltd. | Erection, assistance during commissioning of 1 x 50 TPH, 51 Kg/cm2, 405 Deg. C., Bi-Drum AFBC Boiler at JSL Ltd, Jajpur, Orissa, | 1,10,48,135.00 |
Year | Company | Work | Value in INR |
---|---|---|---|
30-Jun-12 | Thermax Engineering Construction Company Ltd. | Erection, testing and commissioning of 1 x 165 TPH CFBC Boiler for the 1 x 25+ 1 x30MWCPP at J K Papers Ltd, Rayagada, Orissa | 2,44,20,000.00 |