  • Renovation and Modernization(dismantling and installation of TG set with Deck Modification) of unit#5(210MW) at Bandel thermal power station at west Bengal thermal power corporation limited
  • Erection, Testing & Commissioning for 2×350 MW STG Package including Auxiliaries like BFP, DE-aerator, Drive Turbine etc including Lube Oil Piping at Ind-Barath project at Sahajbahal village
  • Erection, Testing and commissioning of Gas Turbine and balance of Plant / Power Cycle for our 225 MW Gas Based CCPP at Kashipur, Udham Singh Nagar District, Uttrakhand
  • Installation of 290 MW Steam Turbine, Generator and associated equipment’s of Unit # 2 Condenser # 2 including reassembled skids, interconnecting piping, valves, fittings, pumps, expansion joints, Condenser and other related equipments includes handling, setting, assembly, alignment, coupling and erection of equipment’s at Dabhol Power project, Maharashtra.
  • Erection, Testing & Commissioning of W.German-KWU-design : 2 X 210 MW Turbine, Generator Feed, Pumps, Condenser, Rotating & Static Auxiliaries & Associated HP & LP Piping Unit-I, II & V at Wanakbori TPS
  • Erection, Alignment, Testing & Commissioning of Russian Design: 3 x 210 MW Turbine, Generator, Exciter Feed Pumps, Condenser, Auxiliaries and associated piping Turbine boxed up at Kolaghat TPS.
  • (British design : 3 X 120 MW) Turbine Generator, Piping, HV, LV Bus duct, Control and Power Cables.( E.S.P. for one set only ) Major Modification conveyor done by site fabrication High pressure welding & S.R.done by own staff at Santaldih TPS.
  • Erection, Testing & Commissioning of Czek design: 2 X 110 MW Turbine, Generator, Condenser Auxiliaries and Piping at Patratu TPS.
  • Erection, Testing & Commissioning of Condenser, Turbine, Generator, Exciter, Auxiliaries and Piping for 1 x 60 MWTG set, Unit II at Bongaigaon Thermal Power Station, Salakati, Assam
  • Erection, Testing and commissioning and 3 x 34 MWTG sets at DESU /WHRP
  • Erection, Testing, Pre-Commissioning & Commissioning of 1 x 33 MW Steam Turbo-Generator sets Turbine, Generator, Condenser, Pumps, Ejector, Lube Oil Tank, Cooler, Boiler Feed Water Pump, Generator cooler, Valve, Piping including Thermal Insulation at M/s HEG, Mandideep in Madhya Pradesh
  • Erection, Testing & Commisisoning of 25 MW Chinese made Steam Turbine at Jindal Strips Ltd., Raigarh
  • Erection, Testing & Commissioning of 21 MW TG unit (Toyo Denki make) with auxiliaries & piping Turbine & Generator at Century pulp & Paper, Lalkua
  • Erection, testing, commissioning of surface condensers, steam turbines, turbo blowers, pumps & auxiliaries including condensate extraction pumps, including Electrical and Control & Instrumentation equipments, piping, application of thermal insulation, final painting, assistance for PG Test etc and handing over of 3 x 18 MW Turbo Blower set at Steel Authority of India Ltd (SAIL), Rourkela Steel Plant, Rourkela, Dist. Sundergarh (Orissa)
  • Erection, Testing & commissioning of Turbine, Generator & Exciter, Auxiliaries and piping for 3 x 16 MW unit of Bongaigaon Refinery Project.
  • Erection &Commissioning of STG (1 x 6 MW) Triveni steel at Monet Ispat— Raipur

Few Erection, Testing & Commissioning jobs of Gas Turbine & Generator

  • Erection, Testing & Commissioning of FR-6 Gas Turbine-Generator sets & their Aux., BOP with related Piping etc for 2 x 30 MW EPCC Package-7 (GTG&HRSG) at IOCL, Gujarat Refinery, Jawaharnagar, Vadodara.
  • Erection and Commissioning job of GT# 7 at RIL Hazira
  • Erection and commissioning of both GT-IV & V (M/s BHEL supplied Frame-VI Gas Turbines) at IOCL Gujarat Refinery
  • Erection, Testing & Commissioning together with material handling of 1 x 21 MW GTG (Frame-V GT) with auxiliaries & piping etc for 1 x 21 MW GTG based co-generation Captive Power Plant of BRPL-DHDT project at Bongaigaon Refinery & Petrochemicals Limited
  • Erection of 3 x 32 MW Nuovo Pignone (Italy) make Gas Turbine Generator and auxiliaries and piping in CPP plant at Reliance Jam nagar
  • Erection of 2 x 22.5 MW Westing House Gas Turbine (Combined Cycle) at Namrup Thermal Power Station.
  • Erection & Commissioning of Gas Turbine Generator Frame-V and Borsig Compressor at Indian Farmers Fertilizers Corporation Limited (IFFCO)Aonla.
  • Erection & Commissioning of Frame V Gas Turbine and Generator at National Fertilizers Limited (NFL), Vijaipur
  • Erection of Frame VI Gas Turbine, Load Gearbox accessory gear box at Rajasthan State Electricity Board, Jaisalmer
  • Erection / Installation, testing & commissioning including Material Handling, Electrical and C&I Job etc. of 1 X 21 MW GTG (Frame-V) with all accessories at GOTTSECL, Baramura, Tripura.
  • Erection of 3 x 32 MW Nuovo Pignone (Italy) make Gas Turbine Generator and auxiliaries and piping in CPP plant at Reliance Jamnagar.